Sabina Gold & Silver Finalizes Lump Sum Bid Agreement for Physical Plant Construction

2023-01-13 10:44:17 By : Ms. Ivy Zhuang

C$139 million contract completed with CGT Industrial Ltd.~ ~Winter Ice Road Construction Begins~

VANCOUVER, British Columbia, Jan. 12, 2023 (GLOBE NEWSWIRE) -- Sabina Gold & Silver Corp. (“Sabina”) or (the “Company”) (SBB – TSX/ SGSVF - OTCQX) is pleased to announce it has finalized the lump sum contract with a northern constructor to build the process plant and ancillary buildings at its Goose Mine on its 100% owned Back River Gold District in Nunavut, Canada. The Goose Mine is the Company’s first mine on the 80 km long Back River Gold District, a multi-generational mining district with a demonstrated high-grade world class gold endowment.

CGT Industrial (“CGT”)  is composed of Clark Builders, Gisborne Industrial Construction Ltd. and PTW Energy Services, leaders in their respective fields of construction including concrete, buildings, mechanical and electrical services. Collaborating as a single entity, CGT provides clients with a wide selection of services and the convenience and efficiency of working with a single, expert organization. CGT has extensive experience in mining projects in the Western Arctic dating back as far as 1982.

CGT has provided Sabina with a fixed priced contract of CAD $139 Million for materials and labour to construct the process plant including: crushing circuit, grinding circuit, CIL circuit, pre-leach and tails thickener with tails pumping, gold room, E-houses, control room, O2 plant, fresh water, truck shop, and fire water systems. Additional scope has been added to the original bid proposal which includes the power plant and the Port fuel farm. The contract includes an agreed rise and fall mechanism and other mechanisms to adjust for changes in bid quantities due to design growth and scope changes. These components make up approximately 85% of the direct works on site.

“We are happy to finalize the terms of our agreement with CGT,” said Bruce McLeod, President & CEO. “CGT brings its considerable experience in construction, particularly in the North, to our project. Sabina is unique in that our Project is largely based on self-delivery for the majority of civil works and for underground development. CGT’s experience in Northern plant construction de-risks the execution of the Project and provides a higher degree of certainty to the associated costs. Additionally, the construction of our Winter Ice Road “WIR” to transport equipment and supplies to the Goose site has begun.”    Winter Ice Road (“WIR”)

Work on Sabina’s WIR is underway, with construction commenced from both the Goose and the Port Facility sites. Transportation operations are expected to start in February 2023 with an anticipated 1300 loads being moved from the Port to Goose.

2022 was a significant year for the Company and many initiatives were achieved. Sabina procured 95% of all materials and equipment required for construction, earthworks were significantly completed – particularly at the plant & accommodation complex site, the Company went from 26 full time employees in March 2022 to now over 160 employees – and still recruiting. The underground ramp has been developed and advanced (two years ahead of time) to enable the potential optimization of the mine plan. Exploration success continues with work in 2023 focusing on George, Sabina’s potential second mine on the District. In addition, Sabina’s significant efforts in environment and community relations over the years were recognized with the 2022 PDAC Sustainability Award.

For a Photo Gallery of 2022 site activities, please see here https://www.sabinagoldsilver.com/assets/docs/Sabina%20Photo%20Gallery%20Update.pdf

SABINA GOLD & SILVER CORP

Sabina Gold & Silver Corp. is an emerging gold mining company that owns 100% of the district scale, advanced, high grade Back River Gold District in Nunavut, Canada.

Sabina filed an Updated Feasibility Study (the “UFS”) on its first mine on the district, the Goose Mine, which presents a project that will produce ~223,000 ounces of gold a year (first five years average of 287,000 ounces a year with peak production of 312,000 ounces in year three) for ~15 years with a rapid payback of 2.3 years, with a post-tax IRR of ~28% and NPV5% of C$1.1B at a gold price of $1,600 USD. See “National Instrument (NI) 43-101 Technical Report – 2021 Updated Feasibility Study for the Goose Project at the Back River Gold District, Nunavut, Canada” dated March 3, 2021.

The Project has received all major permits and authorizations for construction and operations.

The Company has arranged a comprehensive project financing package comprised of:

A US$425 million senior secured debt facility, gold prepay and stream package with Orion Mine Finance and Wheaton Precious Metals Corp.; and

US$221 million in equity including Zhaojin’s participation.

The Company is also very committed to its Inuit stakeholders, with Inuit employment and opportunities a focus. The Company has signed a 20-year renewable land use agreement with the Kitikmeot Inuit Association and has committed to various sustainability initiatives under the agreement.

The Company continues to advance exploration and project optimization, including advancing the planned plant expansion to 4,000 tpd from Year two to initial startup.

All news releases and further information can be found on the Company’s website at www.sabinagoldsilver.com or on SEDAR at www.sedar.com. All technical reports have been filed on www.sedar.com

For further information please contact:

Nicole Hoeller, Vice-President, Communications:        1 888 648-4218

Forward Looking Information This news release contains “forward-looking information” within the meaning of applicable securities laws (the “forward-looking statements”), including, but not limited to, statements related to the expected use of proceeds of the Offering and the projections and assumptions of the results of the UFS. These forward-looking statements are made as of the date of this news release. Readers are cautioned not to place undue reliance on forward-looking statements, as there can be no assurance that the future circumstances, outcomes or results anticipated in or implied by such forward-looking statements will occur or that plans, intentions or expectations upon which the forward-looking statements are based will occur. While we have based these forward-looking statements on our expectations about future events as at the date that such statements were prepared, the statements are not a guarantee that such future events will occur and are subject to risks, uncertainties, assumptions and other factors which could cause events or outcomes to differ materially from those expressed or implied by such forward-looking statements. Such factors and assumptions include, among others, the uncertainty of production, development plans and costs estimates for the Back River Gold Project; discrepancies between actual and estimated mineral reserves and mineral resources, between actual and estimated development and operating costs; the interpretation of drill, metallurgical testing and other exploration results; the ability of the Company to retain its key management employees and skilled and experienced personnel; exploration, development and mining risks and the inherently dangerous nature of the mining industry, and the risk of inadequate insurance or inability to obtain insurance to cover these risks and other risks and uncertainties; property and mineral title risks including defective title to mineral claims or property; the effects of general economic conditions, commodity prices, changing foreign exchange rates and actions by government and regulatory authorities; and misjudgments in the course of preparing forward-looking statements. In addition, there are known and unknown risk factors which could cause our actual results, performance or achievements to differ materially from any future results, performance or achievements expressed or implied by the forward-looking statements. Known risk factors include risks associated with exploration and project development; the need for additional financing; the calculation of mineral resources and reserves; operational risks associated with mining and mineral processing; fluctuations in metal prices; title matters; government regulation; obtaining and renewing necessary licenses and permits; environmental liability and insurance; reliance on key personnel; the potential for conflicts of interest among certain of our officers or directors; the absence of dividends; currency fluctuations; labour disputes; competition; dilution; the volatility of the our common share price and volume; future sales of shares by existing shareholders; and other risks and uncertainties, including those relating to the Back River Project and general risks associated with the mineral exploration and development industry described in our Annual Information Form, financial statements and MD&A for the fiscal period ended December 31, 2021 filed with the Canadian Securities Administrators and available at www.sedar.com. Although we have attempted to identify important factors that could cause actual actions, events or results to differ materially from those described in forward-looking statements, there may be other factors that cause actions, events or results not to be as anticipated, estimated or intended. There can be no assurance that forward-looking statements will prove to be accurate, as actual results and future events could differ materially from those anticipated in such statements. Accordingly, readers should not place undue reliance on forward-looking statements. We are under no obligation to update or alter any forward-looking statements except as required under applicable securities laws.

Bruce McLeod, President & CEO 1800-555 Burrard Street, Two Bentall Centre Vancouver, BC V7X 1M9 Tel 604 998-4175 Fax 604 998-1051 http://www.sabinagoldsilver.com

AUY vs. AEM: Which Stock Is the Better Value Option?

Taiwan Semiconductor Manufacturing reported a record net profit and beat analysts’ expectations for its fourth quarter but warned of waning demand in 2023. Taiwan Semiconductor (ticker: TSM), the world’s largest contract chip maker and a main rival to Intel (INTC) and Samsung Electronics (KRX), said net profit for the quarter was 295.90 billion Taiwanese dollars ($9.72 billion), up 78% from the prior year. Analysts had expected profit of 288.08 billion Taiwanese dollars according to a poll of analysts by S&P Global Market Intelligence.

One company has celestial aspirations, while the other is looking to get back its positive momentum.

Overall, the December CPI report roughly met Street expectations, but there is still a lot of bearish commentary going around right now. Many financial prognosticators are forecasting another tough year for the stock market as the prospect of a recession looms large. However, that is certainly not the view of HSBC's Max Kettner. The strategist points out that the harbingers of doom are unlikely to be surprised by more negative developments with the markets already accounting for the fatalistic o

Units of KNOT Offshore Partners (NYSE: KNOP) are plummeting today, down by nearly 40% as of 10:30 a.m. ET. The sharp move lower came after the master limited partnership (MLP) focused on the shuttle tanker market made a significant distribution cut. KNOT Offshore Partners declared its fourth-quarter distribution payment.

MercadoLibre (NASDAQ: MELI) stock popped over 8% today on news from a Brazilian competitor. In the below video, I share this news and how it could impact MercadoLibre going forward. I also provide a background of the business, important growth demographics, valuation, and a chart to see where the stock could be headed next.

Riot closed the day almost 15% higher, while Silvergate cruised to a nearly 13% increase. Riot and Silvergate are rather different animals. Silvergate is in many ways a traditional bank but is often lumped in with other crypto assets since its Silvergate Exchange Network (SEN) is a real-time payments platform that services users from cryptocurrency exchanges and institutions.

Nio stock has solid chances of a recovery in 2023 thanks to new launches and a focus on market share.

EV maker Tesla's Shanghai gigafactory expansion is reportedly delayed amid data concerns.

Let's discuss the prospects of three high-yield stocks, which are offering dividend yields above 5% and are attractively valued right now. Thanks to the high dividends of these stocks, their shareholders are adequately compensated while waiting for the stock prices to appreciate. Verizon Communications , which was created by the merger between Bell Atlantic and GTE in 2000, is one of the largest wireless carriers in the U.S. The company generates approximately 75% of its revenue from its wireless business and the remaining 25% from broadband and cable services.

Oil stocks dominate this list of today's top growth stocks. Across all sectors, 21 firms have estimates of 100%-1,220% for 2022.

(Bloomberg) -- Bed Bath & Beyond Inc. is speaking with potential lenders that would finance the company during bankruptcy proceedings, according to people with knowledge of the matter.Most Read from BloombergElon Musk Fan With 2,900% Gain Sees $1.5 Million Wiped AwayUS Inflation Cools Again, Putting Fed on Track to DownshiftT-Mobile Considers Buying Ryan Reynolds’s Mint MobileUniversal Plans New Family Resort in Texas, Las Vegas Horror AttractionBond Yields Tumble as Traders Dial Back Fed Wagers

Home improvement retailer Home Depot is making a nationwide change to how it pays hourly employees next week. The move was first reported by Business Insider.

The bank is among those expected to benefit most from the Federal Reserve’s string of interest-rate increases.

Stocks were up this week, ahead of today’s inflation data. The gains reflected investor optimism that inflation will continue to scale back – a sentiment that was backed up by the actual numbers. The rate of price increases for December came in at a 0.1% decrease month-over-month, and at an increase of 6.5% annualized. These were exactly in-line with the forecasts, and mark a slowing down of inflation going forward. The slower pace is good news. With this scale-back – inflation’s annualized incr

The pandemic set off an intense race among pharmaceutical companies to produce effective vaccines against COVID-19. Novavax's critical weakness continues to be its manufacturing operations, which since mid-2021 have struggled to scale up to meet the company's ambitions -- never mind the purchase orders for which it already received payment from customers. Other major international purchasers inked deals for similarly large quantities in 2020 and 2021, driving Novavax's trailing-12-month revenue to grow to more than $1.8 billion, though it remains unprofitable.

Shares of Lumen (NYSE: LUMN) suffered a precipitous valuation decline in 2022. The telecommunications company's share price fell 58.4% across last year's trading, according to data from S&P Global Market Intelligence. Amid macroeconomic pressures including inflation and rising interest rates, Lumen's stock lost ground in conjunction with the broader market last year.

(Bloomberg) -- The US will avoid a recession this year as the Federal Reserve controls inflation, giving the stock market a boost, according to John Rogers, chairman and co-chief executive officer of Ariel Investments. Most Read from BloombergElon Musk Fan With 2,900% Gain Sees $1.5 Million Wiped AwayUS Inflation Cools Again, Putting Fed on Track to DownshiftT-Mobile Considers Buying Ryan Reynolds’s Mint MobileUniversal Plans New Family Resort in Texas, Las Vegas Horror AttractionBond Yields Tum

The business model is quite strong, but unless the broader economy improves, the stock price will not recover

Shares of Taiwan Semiconductor are moving higher even amid the company's weak guidance for fourth-quarter earnings.